Source-audited public forecasts
Fusion promise drift
A dated record of what fusion programs said would happen—and what actually did. Vertical position shows the years remaining when each forecast was made. Checks mark observed achievements; X marks a target date that passed without a matching public achievement verified in this audit.
Outcome
✓observed achievement
×date passed; no verified achievement
○not yet due
Connections
same performance milestone
Diagonal guides = fixed target year
Scope rule: The chart includes only dated performance claims: prospective net-electricity, fusion-gain, plasma-Q, and Lawson milestones, plus observed NIF target-gain achievements. Construction, first-plasma, commissioning, and grid-delivery dates are excluded because they do not establish fusion performance. Pacific Fusion remains unplotted because the reviewed source provides no dated target.